            - December - EMT request project $$ from MPM for specific projects
 - MPM requests project $$ for specific projects
 - MPM requests project $$ from the Budget Office (lump sum in GA under CAS Project Fund Code)
 - EMT comes back when "ready to launch"
 - If request receives MPM Approval:
- Frank request Project ID and Speed Type from Controllers
 - Frank request Budget Office to move funds to that Speed Type
 - Frank notifies requestor where approved funds are
 - Frank tracks project budget and requests in same spreadsheet as contingency $$
 
 
 
      
   
    
      
  
          
    
            Notes
- Michael requests bucket of $$ - meets to review specific requests that make up requested amount. Identifies other potential initiatives.
 - "Ready to Launch" implies the project is no longer a concept but has detail for scope, dates, resources, etc... and possibly real quotes
 - Projects get a Speed Type that falls under managing department. Non-UITS depts have 1 project bucket and not separate projects.
 - Project $$ are typically meant to be spent in one fiscal year. There are exceptions for large multi-year projects.
 - Frank needs to let Jean know when project budgets are created or inactivated. Jean to update IT Procurement web site.
 - Should we move requested $$ when approved OR actual $$ when req is ready? Once funds are in project fund they can't easily move back.